SOUTH PUMICESTONE REHABILITATION AND SEAWALL RENEWAL
CLIENT: MORETON BAY REGIONAL COUNCIL
DATE OF COMPLETION: SEPTEMBER 2013
WORK SCOPE:
-
REMOVAL OF EXISTING SHORELINE PROTECTION, EXCAVATION TO REAR OF SEAWALL
-
INSTALLATION OF GROUND ANCHORS TO TIE BACK EXISTING SEAWALL
-
INSTALLATION OF VINYL SHEETPILES TO TOE OF EXISTING WALL
-
FORM AND CAST CONCRETE TO NEW BOTTOM STEP
-
ROCK BEACHING AND PROTECTION TO CULVERT OUTFALL
-
BEACH NOURISHMENT
PROJECT DRAWINGS: SOUTH PUMICESTONE REHABILITATION
ANTI SCOUR ROCK PROTECTION
Vinyl Sheet pile installation
Equipment used:
-
7.8t excavator for excavation
-
Sheet Pile Vibrator
Application:
-
Support for new seawall footing
-
Prevents scour of sand behind the wall
Ground anchor installation
Equipment used:
-
7.8t excavator for excavation
-
4t excavaator with rock hammer
-
30t jack for post instalation tensioning
-
5t jack for lock off loads
Application:
-
Support for existing seawall
-
Prevents longditudinal moment
Concreting in the inter tidal zone
Works Completed:
-
120m and 105m sections of two teir step
-
Culvert base with 500mm of rock
Solutions to tidal interference:
-
Sheet pile bund wall to allow longer working times
-
Organisation of work around out going tides